Payback & ROI Calculator

Will a reliability improvement pay for itself, and how fast? Results update as you type. Free, and no account is needed to see them.

  1. Calculate Downtime Cost
  2. Compare Options
  3. Write the Case
  4. Review With Finance

Free tool · About 2 minutes

Test an Improvement

Example numbers are filled in. Replace them with yours. Your figures stay in this browser unless you save or download.

Describe today's losses
More optionsSavings build up over 2 years · 5 years at 10% · 70% chance it works
Cases to show
How fast savings arrive

Does It Pay Back?

Example numbers

Pays back in

1 year 11 months

NPV over 5 years
$130,000
ROI over 5 years
148%
  • Today's loss $250,000 a year (100 h × $2,500/h) → $175,000 after a 30% cut. Savings $75,000 a year once fully running, $65,000 after ongoing cost.
  • Conservative case (15% cut, half the expected): pays back in 3 years 2 months, NPV $20,900.
  • It pays for itself over 5 years if it cuts the loss by at least 12.1%.
Yr 012345Payback

Cumulative cash by year, before discounting. Year 0 is the upfront cost.

Savings build up over 2 years (25%, 75%, then full) · 5 years at 10%

More results

Year by Year (Expected Case)

YearSavingsOngoing costNetCumulativeDiscounted
0 (upfront)——−$50,000−$50,000−$50,000
1$18,750−$10,000$8,750−$41,250$7,955
2$56,250−$10,000$46,250$5,000$38,223
3$75,000−$10,000$65,000$70,000$48,835
4$75,000−$10,000$65,000$135,000$44,396
5$75,000−$10,000$65,000$200,000$40,360

Cases

CaseCutSavings a yearPaybackNPVROI
Conservative15%$37,5003 years 2 months$20,90024%
Expected30%$75,0001 year 11 months$130,000148%

Risk-adjusted NPV: $64,500, with a 70% chance it works as planned. Costs are counted in full; savings at 70%.

You could spend up to $180,000 upfront and still break even over 5 years.

What Moves the Answer Most

NPV when each one is 20% lower or higher
Driver20% lower20% higher
Yearly savings (today's loss or the cut)$86,200$173,000
Discount rate$141,000$119,000
Upfront cost$140,000$120,000
Ongoing cost per year$137,000$122,000
Show the math

Today's loss = hours a year × cost per hour + other yearly costs
Savings in year t = loss × cut × build-up(t)
Net in year t = savings − ongoing cost
NPV = −upfront + Σ net ÷ (1 + rate)^t
ROI = NPV ÷ (upfront + Σ ongoing ÷ (1 + rate)^t)
Payback = when cumulative net cash reaches zero

Keep a Copy

Free account needed. Your inputs stay on this page and the action finishes once you're signed in.

Open an Older Saved Scenario

Next: Write the Case

Turn these numbers into a one-page business case for your plant manager or controller.

Open the Business Case Template

Need a better cost per hour first?

Work It Out in the Downtime Cost Calculator
How this is calculated

Today's loss is downtime hours times your cost per hour, plus other failure costs (or, from failure history, failures a year times the cost of each). The improvement removes the share you expect. Savings build up over two years unless you change it. Payback counts the upfront cost back from those yearly savings after ongoing costs. NPV discounts each year's net savings at your rate. ROI is NPV divided by the discounted costs.

What this does not include

Tax, depreciation, financing and inflation; the value of reduced safety and environmental risk; savings outside the downtime you entered. Finance may adjust for these. Results are estimates from your inputs, not a guarantee of savings.

Worked Example & More Details

Worked Example

Illustrative numbers, not from any plant. A packaging line loses about 100 hours a year to gearbox failures, at $2,500 an hour (from the Downtime Cost Calculator): $250,000 a year. A condition-monitoring route plus a planned gearbox rebuild costs $50,000 up front and $10,000 a year. The team expects it to remove 30% of that loss once it is fully working: $75,000 a year.

Savings: $18,750 (year 1) · $56,250 (year 2) · $75,000 (year 3 on)
Net after $10,000 a year: $8,750 · $46,250 · $65,000
$50,000 back in 1 year 11 months · NPV (5 years, 10%) ≈ $130,000 · ROI ≈ 148%

It pays for itself if it removes at least 12.1% of the loss. If it only removes half of what the team expects (15%), payback stretches to 3 years 2 months.

Questions That Usually Come Up

Why is payback longer than upfront cost divided by yearly savings?

Because savings take time to build up. The calculator counts 25% of the full saving in year 1 and 75% in year 2. If yours will be at full effect from the start, choose "Full savings from year 1" under More options.

What cut should I assume?

Base it on the failures the improvement actually addresses, and on results from similar fixes at your plant. If you're unsure, look at the break-even line: it tells you how good the fix has to be.

Where does the cost per hour come from?

Use the Downtime Cost Calculator, or a figure your finance team already accepts. If it already includes repairs and scrap, don't add them again here.

What is risk-adjusted NPV?

NPV if there's a chance the improvement doesn't deliver. It counts the costs in full and only your chosen share of the savings.

Should I use failure history or hours a year?

Hours a year is quicker. Failure history shows which failure modes drive the loss and how much a bad year could cost, if you have counts from your work orders.

Pays back in 1 year 11 months. NPV $130,000 over 5 years, ROI 148%. These are example numbers.